Ahead of Oracle’s earnings report, the company put out a statement countering a Bloomberg article noting OpenAI pulled back on a deal because facilities didn’t have the latest Nvidia GPUs. Bloomberg reported that the companies ended plans to expand a data center in Abilene, TX. Oracle reportedly secured the site, ordered the hardware and spent on construction and staff with the expectation of expansion in the future.
Oracle shot back in a post on X and said the Bloomberg report, followed by CNBC, was false and incorrect. Oracle said existing projects were on track but didn’t address the expansion plans. Oracle said:
“Recent media activity about the Abilene site are false and incorrect. First, Crusoe and Oracle are operating in lockstep to deliver one of the world's largest AI Data centers in Abilene at record-breaking pace. Two buildings are completely operational and the rest of the campus is on track. Second, Oracle has completed leasing for the additional 4.5GW to deliver on our commitments to OpenAI.”